I am R. A. Rajeev, IAS Retd.; Founder Director, Urban World Consulting Pvt. Ltd, working for betterment of Cities by redesigning them to be more inclusive.
This young boy is a daily traveler in
#MumbaiMetro
, goes to attend tuition. It was a pleasant site to witness him parking his bicycle easily. He looked very comfortable with the metro services. All the best to him.
@MMMOCL_Official
@pedalandtring
@PMOIndia
I am happy that Hon
@CMOMaharashtra
is inaugurating the second arm of Kalanagar flyover tomorrow. It is going to help BKC visitors a lot and also reduce congestion on Kalanagar junction.
@MMRDAOfficial
@AUThackeray
@MMRDAOfficial
taking Mumbai to Mumbai2.0 . The shape of Metro stations to come up in future is below. So Mumbaikars, please fasten your seat belts and welcome new Metro in city life.
‘I am happy that today our dream of bringing ‘Metro on track’ is becoming a reality on my last day in office’ said
@MMRDAOfficial
yesterday after
@CMOMaharashtra
flagged off the trial run of metro on 20 kms track, the longest trial run done by any Metro in India.
@MMRDAOfficial
is executing pavement improvement and cycle track work in BKC. Cycles for last mile connectivity were first introduced in BKC. With integrated cycle track alongside footpath developed in scientific way is expected to be successful.
The tallest tree in Wales got damaged by a storm and was supposed to be cut down, instead chainsaw artist Simon O'Rourke found a better solution to symbolize the tree’s last attempt to reach the sky.
Creativity at its best!!
@MMRDAOfficial
trying to finish line 2A platform works in time. Roof portal work completed at 4 stations viz: Anand Nagar, Simpholi, IC Colony & Eksar. Work at Mahavir Nagar, Don Bosco is likely to be completed by 10th Dec. Work at Rushi Sankul also started.
@MMRDAOfficial
creates another history by reconstructing the RST 05 indigenously and doing the trial run successfully today, which was cannibalised by Scomi and was never put to use since its import. This is a great example of ‘atmanirbhar’ Bharat!
@MMRDAOfficial
appoints consultants for preparing DPR for Nariman Point to Colaba bridge in next four months.
@AUThackeray
has been consistently following it up with MMRDA.
As per Hon CM’s directions,
@MMRDAOfficial
is taking utmost care to protect Covid facility created at BKC. It can sustain the wind velocity of 80-100 kmph only. As a precautionary measure
@mybmc
is shifting 150 patients who are admitted here.
@AUThackeray
@CMOMaharashtra
There are many examples of widening of roads in cities due to increase in number of vehicles, but there is no example of increasing the width of footpaths as people have increased in the city due to new residential complexes coming up. Is it not strange? Just a thought.
I think seeing the demand of commuters, services of Metro line 2A should be extended till midnight. Last service closes by 9.45 pm which too early for western suburb residents.
On Eastern Express Highway, the completed flyover is waiting for auspicious time for inauguration! Till that time the traffic snarl will continue!!
@MMRDAOfficial
@mybmc
@mumbaitraffic
Congratulations to each Mumbaikar! Today Metro One has achieved 600 million commuter mark in less than 2000 days! First to achieve this in India! Many more firsts in urban mobility are in the offing!
Sharing video of phase 1 of BKC Covid hospital....it’s 7.37 pm and dinner is being served. The whole hospital is on cctv being monitored 24*7
@mybmc
@MMRDAOfficial
@CMOMaharashtra
Line 2A trial section from Dahisar to Kamraj Nagar and upto depot loop line has been energized at 25KV today , trials will start on 31st May from charkop depot to aarey as OHE of Line-7 has also been successfully energised.
@CMOMaharashtra
@mieknathshinde
@MMRDAOfficial
completes launching of all 7 girders at Anand Nagar subway, Thane part of Kopri ROB project yesterday night. Job of two nights performed by our committed team of engineers in one night!
@CMOMaharashtra
@mieknathshinde
@AUThackeray
So nice to see the dream coming to reality! The MoU was signed by me in September, 2020. Thank you
#UNTIL
, Finland’s VTT, Mumbai’s Earth5R and
@MMRDAOfficial
for starting the same. This could not have happened without support of
@AUThackeray
.
We assure every Mumbaikar that Western Express Highway will be improved to international standards before Monsoon of 2020! Everyone’s cooperation is solicited.
OHE of Line 7(Aaray to Dahisar) charged successfully today. Also CEIG sanction for charging OHE on line 2A , from Charkop Depot entry point to Dahisar ( E) received. It will be charged tomorrow, ready for trial run on 20 kms anytime thereafter.
@CMOMaharashtra
@MMRDAOfficial
Three Indian Companies have shown interest in designing and developing Mono rail rolling stock! After giving first order for make in India metro coaches for Line 2 and 7,
@MMRDAOfficial
hopefully will get develop mono rail coaches in India.
Much needed in Mumbai, where there is shortage of space everywhere. These can be pressed and flattened by heavy rollers and then stacked at a junkyard, will occupy less space. Keep it on boss!!
Some wanted pictures Here are a few.
@mybmc
and
@MumbaiPolice
trying to clean up. Will be at it daily. Task is huge but we will achieve. With your support 🙏
@MMRDAOfficial
in another venture signed an MoU with
@Earth5R
in collaboration with UNTIL and Marine Debris Partnership forum for removal and recycling of non biodegradable material from Mithi river, in presence of
@AUThackeray
and
@anilparab
ji.
This needs to be improved! There is no space for people to walk on footpath near under construction DN Nagar metro station in Andheri West. The road surface is also not in proper condition.
@MMRDAOfficial
is requested to look into.
@MMRDAOfficial
calls for bids for selection of agency for developing Common Mobility App for MMR, which will be a journey planner and single window for buying all tickets through all mobility providers in MMR. This will be first of its kind in India.
@CMOMaharashtra
@AUThackeray
@MMRDAOfficial
shifts Rail cum Road Vehicle (RRV) mounted on truck on viaduct in Don Bosco-Eksar section to take up the OHE wiring work in the section Mahavir Nagar to Rushi sankul of about 6 RKM, where track has been handed over. Work in full swing.
Congratulations
@MMRDAOfficial
and best wishes for successful operations. For making this possible, contributions of
@Dev_Fadnavis
, Mr UPS Madan ex-MC, Mr Pravin Darade, ex-Adl MC , Mr PKS Murthy, late Sri Maudgil (to name the few), can’t be forgotten.
8 years after
@MumMetro
btwn Versova & Ghatkopar got operational in June 2014, Mumbai to get 2 new Metro lines on Saturday. Read in today's
@HTMumbai
what does it mean and what changed after the first Metro line got operational?
@SachinKalbag
@AUThackeray
@MMRDAOfficial
started kalanagar girder launching at 10.30 pm and finished 3 girders’ launching by 11 am today. Great job by contractors and MMRDA engineers!
At Mankoli junction, there is launching going on of 50 metre long 110 ton in weight steel girder at 0036 hours! MMRDA is making travel to Nashik faster! Long awaited dream coming true!
CMV (Catenary Maintenance Vehicle), known as tower wagon, used in OHE maintenance works. The alternate unloading platform, Stabling Line No 1 and Test Track in the Depot are ready to receive Metro Coaches/track mounted vehicles.
@CMOMaharashtra
@AUThackeray
4 containers with 2 Escalators unit of Aarey station and 3 containers with 1 Escalator unit of Pushpapark station shifted from port and unloaded yesterday night.
@MMRDAOfficial