Explore tweets tagged as #TransbayTransitCenter
@EvanSernoffsky
Evan Sernoffsky
7 years
Photos show cracked beams at #TransbayTransitCenter. Officials will Now seek peer-review of entire design
3
9
13
@urbanlifesigns
Brian Stokle πŸ‡ΊπŸ‡¦πŸŒ³πŸšΆβ€β™€οΈπŸš²πŸšŽπŸš—πŸš…πŸ‘‚πŸ‡ΊπŸ‡ΈπŸ‡¬πŸ‡§πŸ‡«πŸ‡·
8 years
0
0
1
@EvanSernoffsky
Evan Sernoffsky
7 years
From 2015 newsletter, compromised beams at #TransbayTransitCenter shown during construction. The overhead I-beams are now cracked at the center near the column attached to the bus deck
1
10
8
@PeteSuratosNews
Pete Suratos
7 years
Update on #TransbayTransitCenter from temporary terminal on Howard and Main. Tune in to #TodayInTheBay for the latest details @nbcbayarea
1
2
5
@EllaSogomonian
Ella Sogomonian
7 years
#TransbayTransitCenter repairs has closed off Fremont st for at least the next 10 days. NOW at 9:15pm hear from drivers and the longer commute. #SanFrancisco
0
1
0
@EvanSernoffsky
Evan Sernoffsky
7 years
Crews begin work of temporarily shoring up cracked beams over Fremont St. at #TransbayTransitCenter
0
4
2
@CKaftonKTVU
Christien Kafton
7 years
Our first look at the fissure in the beam that cracked in the #TransbayTransitCenter positioned over Fremont St.
0
3
9
@PeteSuratosNews
Pete Suratos
7 years
Just a bit of a traffic problem in SF as the #TransbayTransitCenter gets repairs 😲 Fremont St. btn Howard and Mission will remain closed until further notice @nbcbayarea
0
4
4
@PeteSuratosNews
Pete Suratos
7 years
Crews back at it again the AM at the #TransbayTransitCenter. Two cracked steal beams are still the main concerns @nbcbayarea
0
4
3
@WayneFreedman
Wayne Freedman
7 years
Welcome to #TransbayTransitCenter commute madness at 5pm. Building closed. Fremont Street, too. Cracked beams create engineering riddle and embarrassment. How did this happen to SF’s newest, glitziest gem? #abc7now
1
10
12
@ctuan
Michael Cabanatuan
7 years
The Transbay Terminal is being supported now by 6 hydraulic jacks but they’ll be replaced with steel towers β€” made by the company that supplied the two cracked girders. #TransbayTransitCenter
0
8
10
@Luzpenatv
Luz PeΓ±a
7 years
#TransbayTransitCenter | Scenarios behind cracks according to TJPA officials: 1. fabrication issue 2. welding issue 3. installation issue 4. design.
1
0
0
@CKaftonKTVU
Christien Kafton
7 years
1st Street under #TransbayTransitCenter closed after β€œcrews discovered a fissure in one of the steel beams in the ceiling of the third level Bus Deck on the eastern side of the Salesforce Transit Center..”
0
7
5
@urbanlifesigns
Brian Stokle πŸ‡ΊπŸ‡¦πŸŒ³πŸšΆβ€β™€οΈπŸš²πŸšŽπŸš—πŸš…πŸ‘‚πŸ‡ΊπŸ‡ΈπŸ‡¬πŸ‡§πŸ‡«πŸ‡·
8 years
New blog post in the works to discuss the Downtown Rail Extension, the "Pennsylvania Alignment", station location game, and how we get there. Stay tuned. (Thanks to @clem_tillier for the image.) #Caltrain #DTX #TransbayTransitCenter #SaladSpinnerTransitCenter
1
1
13
@CKaftonKTVU
Christien Kafton
7 years
SFPD now closing Beale St, 2nd St. and Fremont St. because of the crack found in the #TransbayTransitCenter expect traffic out of the city to be difficult
1
7
16
@ctuan
Michael Cabanatuan
7 years
Fremont street likely to stay closed beneath Transbay Transit Center u til Oct. 12. No word on the center reopening. #TransbayTransitCenter
1
4
4
@EvanSernoffsky
Evan Sernoffsky
7 years
Morning update from #TransbayTransitCenter: Engineers on scene working on plan to install shoring system under cracked beams. It will consist of columns that go thru bus deck shown above & anchor on Fremont St.
0
6
4
@melissacolorado
Melissa Colorado
7 years
Steel beams in the middle of Fremont Street? That’s part of the plan to fix the #TransbayTransitCenter. The Transbay Joint Powers Authority is working on setting up a shoring system that will β€œhold up, lift the beams that have cracks.” We’ll have more details next on @nbcbayarea
3
4
3
@sfchronicle
San Francisco Chronicle
7 years
What we know about the cracked beams at S.F.'s #TransbayTransitCenter: - Second crack found during safety inspections - Transit center will remain closed through at least Oct. 5 - Fremont Street, which passes under the center, is also closed See more: https://t.co/iPdF5uet8s
2
17
12
@ctuan
Michael Cabanatuan
7 years
Hydraulic jacks being delivered to help shore up #TransbayTransitCenter over Fremont Street.
0
10
12