BerkeleyLabEMP Profile Banner
EMP at Berkeley Lab Profile
EMP at Berkeley Lab

@BerkeleyLabEMP

Followers
3K
Following
1K
Media
1K
Statuses
2K

The Energy Markets & Policy Group at Berkeley Lab conducts technical, economic, and policy analysis of energy topics in the U.S. electricity sector.

Berkeley, CA
Joined January 2016
Don't wanna be here? Send us removal request.
@BerkeleyLabEMP
EMP at Berkeley Lab
22 days
This webinar on grid reslience planning for severe storms is starting NOW! Register and join.
@BerkeleyLabEMP
EMP at Berkeley Lab
1 month
Join us for a webinar on Grid Resilience Planning for Severe Storms in the East and Southeast. June 16, 2–5 pm ET. Experts will discuss planning for severe storms and hurricanes and answer questions from participants. Register:
Tweet media one
0
0
0
@BerkeleyLabEMP
EMP at Berkeley Lab
1 month
Join us for a webinar on Grid Resilience Planning for Severe Storms in the East and Southeast. June 16, 2–5 pm ET. Experts will discuss planning for severe storms and hurricanes and answer questions from participants. Register:
Tweet media one
0
1
3
@BerkeleyLabEMP
EMP at Berkeley Lab
1 month
RT @ENERGY:
0
15
0
@BerkeleyLabEMP
EMP at Berkeley Lab
1 month
RT @ENERGY:
0
249
0
@BerkeleyLabEMP
EMP at Berkeley Lab
1 month
RT @BerkeleyLabETA: The Energy Innovator Fellowship is looking for recent grads to help advance solutions at critical energy organizations.….
0
3
0
@BerkeleyLabEMP
EMP at Berkeley Lab
1 month
Our Joe Rand is quoted on how the interconnection process is going in the Pacific Northwest.
0
0
0
@BerkeleyLabEMP
EMP at Berkeley Lab
3 months
RT @BerkeleyLabETA: @BerkeleyLab Researcher Joe Rand from @BerkeleyLabEMP was named one of the Top 50 Data Changemakers in the Energy Secto….
0
3
0
@BerkeleyLabEMP
EMP at Berkeley Lab
6 months
For even more information, see our landmark research on the interconnection queues, in the report Queued Up. Find also recorded webinars, interactive data sets, and more, at /END
Tweet media one
0
0
0
@BerkeleyLabEMP
EMP at Berkeley Lab
6 months
Policymakers are actively working with stakeholders to improve procedural rules for interconnection but commonly cite the lack of data and transparency as a gap to evidence-based decision-making. We hope these data will shed light on the process. 8/x
Tweet media one
1
0
0
@BerkeleyLabEMP
EMP at Berkeley Lab
6 months
These findings suggest the need for continued interconnection reforms, tighter links between long-term transmission planning and project-level interconnection processes, and more interconnection outcome transparency. 7/x.
1
0
0
@BerkeleyLabEMP
EMP at Berkeley Lab
6 months
A big factor is the cost of network upgrades, which are often billed to project developers to overcome transmission constraints. The wide range of interconnection costs across the country and by situation illustrates the uncertainty and lack of uniformity of the process. 6/x
Tweet media one
1
0
0
@BerkeleyLabEMP
EMP at Berkeley Lab
6 months
Interconnection service can either be firm (capacity) or as-available (energy). One would expect that as-available service would cost less, be approved more quickly, and be less likely to trigger grid upgrades, but our evidence suggests that is often not the case. 5/x
Tweet media one
1
0
1
@BerkeleyLabEMP
EMP at Berkeley Lab
6 months
Wind and solar are seeing the highest costs, whether completed or not. While wind and solar projects that completed the interconnection study process saw interconnection costs making up 6-8% of total project costs, withdrawn projects faced costs of 30-37% of total. 4/x.
1
0
0
@BerkeleyLabEMP
EMP at Berkeley Lab
6 months
Interconnection costs have risen over time. Projects withdrawn in recent years had costs 23% greater than the preceding 5 years and more than double those before 2014. Costs are much greater for withdrawn projects ($373/kW) than for those that completed iX studies ($73/kW). 3/x
Tweet media one
1
0
0
@BerkeleyLabEMP
EMP at Berkeley Lab
6 months
Massive growth in solar and battery deployment has led to the queue backlog. Since 2010 the queue has grown >5X and the process length has doubled. To get more details about what’s going on, we analyzed 5000 interconnection studies to create a first-of-a-kind cost database. 2/x
Tweet media one
1
0
0
@BerkeleyLabEMP
EMP at Berkeley Lab
6 months
We reported earlier on the massive backlog for grid interconnection. To better understand the dynamics and what solutions may be available, we just published “Grid connection barriers to renewable energy deployment in the United States." THREAD!
Tweet media one
1
1
2
@BerkeleyLabEMP
EMP at Berkeley Lab
6 months
RT @eeregov: #DYK: 90% of wind turbine materials can be #recycled. ♻️ . @ENERGY’s latest report backed by @NREL, @ORNL, and @SandiaLabs exp….
0
3
0
@BerkeleyLabEMP
EMP at Berkeley Lab
6 months
Community solar is growing, but customers can be confused when they get separate bills from a community solar company and from their utility. A new report by @NREL and @BerkeleyLab explores issues around consolidated billing for community solar.
Tweet media one
0
1
2