Pattullo Bridge Replacement
@pattulloproject
Followers
2K
Following
58
Media
495
Statuses
656
Follow for the latest updates on the Pattullo Bridge project. Monitored: M-F, 830am-430pm 24/7: 1-844-815-6149 Collection Notice: https://t.co/Xl6GvjlcK7
Joined March 2021
Concrete dry finishing is one of the finishing touches done on the project. The #PattulloBridgeReplacement is made with about 62,400 cubic metres of concrete; that’s enough to fill 25 Olympic swimming pools!
1
0
12
Here’s a look at the bridge’s south approach. The centre median barrier, fencing and lighting is now installed in this area.
0
2
29
At the end of October, these concrete foundations for light posts were delivered for finishing works in @CityofSurrey. Can you spot the embossed retaining wall in the background? Learn more about #PattulloBridgeReplacement's First Nations Art Program: https://t.co/98zp3RE7lc
0
0
8
Taking a moment to appreciate all the dedicated work of crews on the #PattulloBridgeReplacement site. As progress continues on the new bridge, we're sending a big thank-you for the hard work of the entire crew. #BCIB
5
4
35
This photo shows concrete waterproofing underway on the main bridge span in late October. Once waterproofing is complete, crews will place 2 layers of asphalt before painting lines on the roadway
4
3
39
The final stay cable was installed to the #PattulloBridgeReplacement in early October. With all 80 stay cables secured to the tower and bridge deck, work continues on bridge finishings. Visit our website to learn how the stay cables were installed: https://t.co/kMs3tBq5Yu
3
6
27
In late October, after this precast concrete barrier was installed on the bridge approach in @CityofSurrey, crews placed grout in the anchor bolts block outs. This barrier will separate pedestrians and cyclists from vehicle traffic.
1
2
9
The last Rubrica crane has been removed from the bridge deck. A blue-and-yellow specialized lifter could previously be spotted hard at work installing the bridge deck segments. Now that the bridge deck installation is complete, the crane has been disassembled and removed.
2
1
10
Here’s an aerial shot of the #PattulloBridgeReplacement looking towards @New_Westminster. With all 80 stay cables installed, crews continue work on paving and bridge finishings.
1
1
10
📅Tonight! Come to our Public Open House in @CityofSurrey to learn about bridge opening phases & construction activities. Find us at North Surrey Sport and Ice Complex tonight, Wednesday November 5, from 4-7pm.
0
0
2
Check out this new light post installed on Old Yale Road! This light post installation is part of ongoing finishing works happening in the #PattulloBridgeReplacement area in @CityofSurrey.
2
1
8
📅Tonight! Come to our Public Open House in @New_Westminster to learn about bridge opening phases & construction activities. Find us at Anvil Centre tonight, Tuesday November 4, from 4-7pm.
0
0
1
On opening day, the #PattulloBridgeReplacement will connect to King George Boulevard in @CityofSurrey. The new Highway 17 off-ramp will be completed following the partial removal of the Pattullo Bridge. Learn more about bridge opening phases: https://t.co/UZ37Yf1DJY
1
4
21
The last segment of the #PattulloBridgeReplacement’s main span is complete! This means that steel, deck panels and stay cable installation are complete for the main span! Crews can now continue finishing works in this area.
3
3
38
This is an expansion joint installed at the south end of the bridge in @CityofSurrey. Expansion joints are placed between bridge sections to absorb the surface’s natural expansion and contraction due to environmental changes.
1
2
15
Questions about the #PattulloBridgeReplacement? Come to our Public Open Houses to learn about bridge opening phases & construction activities. 📅@New_Westminster: Tuesday Nov 4, 4-7pm @ Anvil Centre 📅@CityofSurrey: Wednesday Nov 5, 4-7pm @ North Surrey Sport and Ice Complex
1
4
7
Join us at our fall Public Open Houses to learn more about #PattulloBridgeReplacement opening phases! 📅@New_Westminster: Tuesday Nov 4, 4-7pm @ Anvil Centre 📅@CityofSurrey: Wednesday Nov 5, 4-7pm @ North Surrey Sport and Ice Complex
1
3
9
Steel girders have now been installed for the new E. Columbia St. exit ramp in @New_Westminster! This new off-ramp will connect northbound vehicles directly to E. Columbia St. eastbound.
2
1
28
Check out our latest flyover video! All 80 stay cables for the #PattulloBridgeReplacement have been installed. Now, crews are hard at work on the connection of the main span into New Westminster, as well as completing the remaining concrete pours & bridge finishing activities.
1
2
15
The final stay cable for the #PattulloBridgeReplacement has now been installed! 🎉 Yesterday, crews installed the last of 80 stay cables to support the bridge deck! Visit our website to learn how the stay cables were installed: https://t.co/kMs3tBq5Yu
3
1
25