pattulloproject Profile Banner
Pattullo Bridge Replacement Profile
Pattullo Bridge Replacement

@pattulloproject

Followers
2K
Following
58
Media
495
Statuses
656

Follow for the latest updates on the Pattullo Bridge project. Monitored: M-F, 830am-430pm 24/7: 1-844-815-6149 Collection Notice: https://t.co/Xl6GvjlcK7

Joined March 2021
Don't wanna be here? Send us removal request.
@pattulloproject
Pattullo Bridge Replacement
3 days
Concrete dry finishing is one of the finishing touches done on the project. The #PattulloBridgeReplacement is made with about 62,400 cubic metres of concrete; that’s enough to fill 25 Olympic swimming pools!
1
0
12
@pattulloproject
Pattullo Bridge Replacement
5 days
Here’s a look at the bridge’s south approach. The centre median barrier, fencing and lighting is now installed in this area.
0
2
29
@pattulloproject
Pattullo Bridge Replacement
7 days
At the end of October, these concrete foundations for light posts were delivered for finishing works in @CityofSurrey. Can you spot the embossed retaining wall in the background? Learn more about #PattulloBridgeReplacement's First Nations Art Program: https://t.co/98zp3RE7lc
0
0
8
@pattulloproject
Pattullo Bridge Replacement
10 days
Taking a moment to appreciate all the dedicated work of crews on the #PattulloBridgeReplacement site. As progress continues on the new bridge, we're sending a big thank-you for the hard work of the entire crew. #BCIB
5
4
35
@pattulloproject
Pattullo Bridge Replacement
12 days
This photo shows concrete waterproofing underway on the main bridge span in late October. Once waterproofing is complete, crews will place 2 layers of asphalt before painting lines on the roadway
4
3
39
@pattulloproject
Pattullo Bridge Replacement
18 days
The final stay cable was installed to the #PattulloBridgeReplacement in early October. With all 80 stay cables secured to the tower and bridge deck, work continues on bridge finishings. Visit our website to learn how the stay cables were installed: https://t.co/kMs3tBq5Yu
3
6
27
@pattulloproject
Pattullo Bridge Replacement
20 days
In late October, after this precast concrete barrier was installed on the bridge approach in @CityofSurrey, crews placed grout in the anchor bolts block outs. This barrier will separate pedestrians and cyclists from vehicle traffic.
1
2
9
@pattulloproject
Pattullo Bridge Replacement
28 days
The last Rubrica crane has been removed from the bridge deck. A blue-and-yellow specialized lifter could previously be spotted hard at work installing the bridge deck segments. Now that the bridge deck installation is complete, the crane has been disassembled and removed.
2
1
10
@pattulloproject
Pattullo Bridge Replacement
1 month
Here’s an aerial shot of the #PattulloBridgeReplacement looking towards @New_Westminster. With all 80 stay cables installed, crews continue work on paving and bridge finishings.
1
1
10
@pattulloproject
Pattullo Bridge Replacement
1 month
📅Tonight! Come to our Public Open House in @CityofSurrey to learn about bridge opening phases & construction activities. Find us at North Surrey Sport and Ice Complex tonight, Wednesday November 5, from 4-7pm.
0
0
2
@pattulloproject
Pattullo Bridge Replacement
1 month
Check out this new light post installed on Old Yale Road! This light post installation is part of ongoing finishing works happening in the #PattulloBridgeReplacement area in @CityofSurrey.
2
1
8
@pattulloproject
Pattullo Bridge Replacement
1 month
📅Tonight! Come to our Public Open House in @New_Westminster to learn about bridge opening phases & construction activities. Find us at Anvil Centre tonight, Tuesday November 4, from 4-7pm.
0
0
1
@pattulloproject
Pattullo Bridge Replacement
1 month
On opening day, the #PattulloBridgeReplacement will connect to King George Boulevard in @CityofSurrey. The new Highway 17 off-ramp will be completed following the partial removal of the Pattullo Bridge. Learn more about bridge opening phases: https://t.co/UZ37Yf1DJY
1
4
21
@pattulloproject
Pattullo Bridge Replacement
1 month
The last segment of the #PattulloBridgeReplacement’s main span is complete! This means that steel, deck panels and stay cable installation are complete for the main span! Crews can now continue finishing works in this area.
3
3
38
@pattulloproject
Pattullo Bridge Replacement
1 month
This is an expansion joint installed at the south end of the bridge in @CityofSurrey. Expansion joints are placed between bridge sections to absorb the surface’s natural expansion and contraction due to environmental changes.
1
2
15
@pattulloproject
Pattullo Bridge Replacement
1 month
Questions about the #PattulloBridgeReplacement? Come to our Public Open Houses to learn about bridge opening phases & construction activities. 📅@New_Westminster: Tuesday Nov 4, 4-7pm @ Anvil Centre 📅@CityofSurrey: Wednesday Nov 5, 4-7pm @ North Surrey Sport and Ice Complex
1
4
7
@pattulloproject
Pattullo Bridge Replacement
2 months
Join us at our fall Public Open Houses to learn more about #PattulloBridgeReplacement opening phases! 📅@New_Westminster: Tuesday Nov 4, 4-7pm @ Anvil Centre 📅@CityofSurrey: Wednesday Nov 5, 4-7pm @ North Surrey Sport and Ice Complex
1
3
9
@pattulloproject
Pattullo Bridge Replacement
2 months
Steel girders have now been installed for the new E. Columbia St. exit ramp in @New_Westminster! This new off-ramp will connect northbound vehicles directly to E. Columbia St. eastbound.
2
1
28
@pattulloproject
Pattullo Bridge Replacement
2 months
Check out our latest flyover video! All 80 stay cables for the #PattulloBridgeReplacement have been installed. Now, crews are hard at work on the connection of the main span into New Westminster, as well as completing the remaining concrete pours & bridge finishing activities.
1
2
15
@pattulloproject
Pattullo Bridge Replacement
2 months
The final stay cable for the #PattulloBridgeReplacement has now been installed! 🎉 Yesterday, crews installed the last of 80 stay cables to support the bridge deck! Visit our website to learn how the stay cables were installed: https://t.co/kMs3tBq5Yu
3
1
25