Explore tweets tagged as #MTCCProjects
@MTCCPlc
MTCC Plc
7 hours
Project Update: Land reclamation for Industrial Zone and Shore Protection Structures at Gdh. Thinadhoo. Construction of the bridge retaining wall is currently underway. Follow more updates at: #MTCCProjects #TeamMTCC #RayyithungeKunfuni
Tweet media one
Tweet media two
Tweet media three
1
2
2
@MTCCPlc
MTCC Plc
9 hours
Project Update: Design and Build of B. Eydhafushi Harbor Construction Works. Installation of concrete blocks required for the construction of quay wall is currently ongoing. Follow more updates at: #MTCCProjects #TeamMTCC #RayyithungeKunfuni
Tweet media one
Tweet media two
Tweet media three
1
0
0
@MTCCPlc
MTCC Plc
2 days
Project Update: Design and Build of B. Maalhos Harbor Repair and Shore Protection. Revetment rock profiling work is currently ongoing. Follow more updates at: #MTCCProjects #TeamMTCC #RayyithungeKunfuni #GaumuBinaakurumugaaMTCC
Tweet media one
Tweet media two
Tweet media three
Tweet media four
0
4
6
@MTCCPlc
MTCC Plc
6 days
Project Update: Construction of R. Maakurathu Police Post Building. We have completed site preparation and earthworks. Roof structure and concrete works are currently ongoing. Follow more updates at: #MTCCProjects #TeamMTCC #RayyithungeKunfuni
Tweet media one
Tweet media two
Tweet media three
Tweet media four
2
16
14
@MTCCPlc
MTCC Plc
20 days
Our DMD, Mr. Mohamed Jamsheed and team met with the GA. Komalaafushi Council today. Discussions focused on the latest project updates. #MTCCProjects #RayyithungeKunfuni
Tweet media one
Tweet media two
Tweet media three
0
0
0
@MTCCPlc
MTCC Plc
19 days
Our DMD, Mr. Ahmed Shareef Abdul Rahman Yoosuf and team met with the R. Dhuvaafaru Council. Discussions focused on the latest project updates. #MTCCProjects #RayyithungeKunfuni
Tweet media one
Tweet media two
Tweet media three
Tweet media four
0
4
5
@MTCCPlc
MTCC Plc
4 days
Project Update: Design and Build of Shore Protection Structures at K. Himmafushi. Revetment and groyne works are currently ongoing. Follow more updates at: #MTCCProjects #TeamMTCC #RayyithungeKunfuni #GaumuBinaakurumugaaMTCC
Tweet media one
Tweet media two
Tweet media three
Tweet media four
0
7
8
@MTCCPlc
MTCC Plc
4 days
Project Update: Subbase preparation works at B. Maalhos Football Ground. Drainage shuttering, concrete works, football ground levelling and compaction works are currently ongoing. Follow more updates at: #MTCCProjects #TeamMTCC #RayyithungeKunfuni
Tweet media one
Tweet media two
Tweet media three
0
9
10
@MTCCPlc
MTCC Plc
9 days
Project Update: Repair Works at K. Thilafushi Jetty. Paving and concrete curb installation work is currently ongoing. Follow more updates at: #MTCCProjects #TeamMTCC #RayyithungeKunfuni #GaumuBinaakurumugaaMTCC
Tweet media one
Tweet media two
Tweet media three
0
7
7
@MTCCPlc
MTCC Plc
10 days
Our DMD, Mr. Ahmed Shareef Abdul Rahman Yoosuf and team met with the Adh. Omadhoo Council today. Discussions focused on the latest project updates. #MTCCProjects #RayyithungeKunfuni
Tweet media one
Tweet media two
Tweet media three
0
8
7
@MTCCPlc
MTCC Plc
6 days
Project Update: Design and Build of Major Roads at L. Fonadhoo - Phase 2. ABC and subbase works are ongoing at Aailee Higun, Mihiri Magu, and Sarahadhee Magu with 74% completion. Overall project progress is 78%. Follow more updates at: #MTCCProjects
Tweet media one
Tweet media two
Tweet media three
Tweet media four
0
8
10
@Xameeru
Xameeru
2 years
ގދ. ރަތަފަންދޫ ގޮނޑުދޮށް ހިމާޔަތް ކުރުމުގެ މަޝްރޫޢުގެ ދަށުން، ގޮނޑުދޮށަށް ވެލި އެޅުމުގެ މަސައްކަތުގެ 87 ޕަސެންޓް ނިމިއްޖެ. އަދި މިހާރު ކުރިއަށްދަނީ ރިވެޓްމެންޓް ޖެހުމުގެ މަސައްކަތް. #MTCCProjects #RayyithungeKunfuni
Tweet media one
Tweet media two
0
0
0
@Waddewaadu
Waadu
2 years
ގދ. ރަތަފަންދޫ ގޮނޑުދޮށް ހިމާޔަތް ކުރުމުގެ މަޝްރޫޢުގެ ދަށުން، ގޮނޑުދޮށަށް ވެލި އެޅުމުގެ މަސައްކަތުގެ 87 ޕަސެންޓް ނިމިއްޖެ. އަދި މިހާރު ކުރިއަށްދަނީ ރިވެޓްމެންޓް ޖެހުމުގެ މަސައްކަތް. #MTCCProjects #RayyithungeKunfuni
Tweet media one
Tweet media two
0
0
0
@MTCCPlc
MTCC Plc
25 days
Our DMD, Mr. Mohamed Jamsheed and team met with the L. Isdhoo Council today. Discussions centered around the latest project updates. #MTCCProjects #RayyithungeKunfuni
Tweet media one
Tweet media two
Tweet media three
0
0
0
@keyodhooRameez
KeyodhooRameez 
2 years
އދ. ކުނބުރުދޫ ގޮނޑުދޮށް ހިމާޔަތް ކުރުމުގެ މަޝްރޫޢުގެ ދަށުން، ބަނދަރު ފުންކުރުމާއި ބިންހިއްކުމުގެ މަސައްކަތުގެ 52 ޕަސެންޓް ވަނީ ނިމިފައި. #MTCCProjects #RayyithungeKunfuni
Tweet media one
Tweet media two
Tweet media three
Tweet media four
0
2
2
@mrsays_
Maimoon
2 years
ގއ. ވިލިނގިލީ ބަނދަރު ތަރައްޤީ ކުރުމުގެ މަޝްރޫޢު (ތިންވަނަ ފިޔަވަހި) ގެ ދަށުން، އައު ހާބަރ ފުންކުރުމުގެ މަސައްކަތް މިހާރު ވަނީ 45 އިންސައްތަ ފުރިހަމަކުރެވިފަ. އަދި، އެއްގަމު ތޮށި ލުމުގެ މަސައްކަތް މިހާރު ވަނީ ފެށިފައ. #MTCCProjects
Tweet media one
Tweet media two
Tweet media three
Tweet media four
0
10
16
@kanburey
Jeyju
2 years
CEO Adam Azim and team has inspected the progress of Gdh. Faresmathoda Airport Development Project. Overall project progress is 95%.#MTCCProjects #RayyithungeKunfuni
Tweet media one
Tweet media two
Tweet media three
Tweet media four
0
0
0
@waappey
waappey
3 years
ހއ. ހޯރަފުށީ އެއަރޕޯރޓް ޖެޓީ ހެދުމުގެ މަޝްރޫއުގެ ދަށުން، ނެރު ފުންކުރުމުގެ މަސައްކަތުގެ 72 ޕަސެންޓް ނިމިއްޖެ. #MTCCProjects #RayyithungeKunfuni
Tweet media one
Tweet media two
Tweet media three
0
0
0
@Sun_Nex
Ali Sanoon
2 years
Thilafushi project site inspection #MTCCProjects @Thifu3Athif
Tweet media one
1
0
1
@MTCCPlc
MTCC Plc
5 days
Project Update: Design and Build of Dh. Kudahuvadhoo Harbor Upgrade. New harbor basin dredging operations and quay wall block installation work is currently ongoing. Follow more updates at: #MTCCProjects #TeamMTCC #RayyithungeKunfuni
Tweet media one
Tweet media two
0
2
3