Follow for the latest updates on the Pattullo Bridge project. Monitored: M-F, 830am-430pm 24/7: 1-844-815-6149 Collection Notice: https://t.co/Xl6GvjlcK7

Joined March 2021
Don't wanna be here? Send us removal request.
@pattulloproject
Pattullo Bridge Replacement
2 days
Check out our latest flyover video! All 80 stay cables for the #PattulloBridgeReplacement have been installed. Now, crews are hard at work on the connection of the main span into New Westminster, as well as completing the remaining concrete pours & bridge finishing activities.
0
2
12
@pattulloproject
Pattullo Bridge Replacement
9 days
The final stay cable for the #PattulloBridgeReplacement has now been installed! šŸŽ‰ Yesterday, crews installed the last of 80 stay cables to support the bridge deck! Visit our website to learn how the stay cables were installed: https://t.co/kMs3tBq5Yu
2
1
25
@pattulloproject
Pattullo Bridge Replacement
10 days
The last pieces of steel of the bridge’s main span were installed last week. Soon, crews will align the main span to be level with the north approach before the final connection.
0
8
23
@pattulloproject
Pattullo Bridge Replacement
16 days
Deck panel & rebar installation has been completed over Front St. and Columbia St. in @New_Westminster. Now, crews are pouring the concrete bridge deck in this area. Seen here, 1,000m3 of concrete has already been poured!
5
3
20
@pattulloproject
Pattullo Bridge Replacement
16 days
This weekend, come find us at the @New_Westminster Cultural Crawl! Our team will be at Anvil Centre to chat with you about the #PattulloBridgeReplacement on October 4 & 5. See you there! 😊
1
1
6
@pattulloproject
Pattullo Bridge Replacement
18 days
Crews continue to make progress with bridge finishing activities, including recently paving the first layer of asphalt on most of the south approach in @CityofSurrey. This bottom layer of asphalt is 50mm thick!
1
3
21
@pattulloproject
Pattullo Bridge Replacement
23 days
Check out the different stages of paving on the bridge deck in @CityofSurrey! Waterproofing can be seen as crews prepare to pave a base layer of asphalt. Waterproofing is a protective layer placed on concrete before the road is paved. On the right, asphalt paving has begun.
0
1
14
@pattulloproject
Pattullo Bridge Replacement
24 days
Check out this birds-eye view of paving work on the bridge’s south approach in @CityofSurrey! Once the bridge deck construction is complete, waterproofing is placed to protect the concrete bridge deck. Then, crews pave the asphalt road surface.
1
0
21
@pattulloproject
Pattullo Bridge Replacement
1 month
Check out our latest flyover video! Starting in @CityofSurrey, the video shows upgrade work on Bridge Road and ongoing construction for the new Hwy 17 off-ramp. New footage of the bridge deck also shows fresh asphalt paving!
1
0
8
@pattulloproject
Pattullo Bridge Replacement
1 month
Here’s a look at progress on the ā€œend spanā€ – the concrete deck is being installed to connect the bridge deck from @CityofSurrey to the bridge tower. Crews are preparing to install the remaining deck panels to continue forming this area of the bridge deck!
4
0
13
@pattulloproject
Pattullo Bridge Replacement
1 month
Bridge finishing works are underway! Here on the south approach, workers are installing safety fencing along the outside edge of the bridge deck.
7
3
39
@pattulloproject
Pattullo Bridge Replacement
2 months
āš ļøTHIS WEEKEND: Full closure of Hwy 17 in @CityofSurrey September 5 at 9pm to September 7 at 5am. Learn more: https://t.co/kcV0wQF5MM Always check https://t.co/TWkz0Jxuf1 for the latest information.
0
2
4
@pattulloproject
Pattullo Bridge Replacement
2 months
Preparation for concrete deck pours is underway for the bridge’s north approach in @New_Westminster! This work includes reinforcing steel placement, formwork construction, and overhang bracket installation.
5
6
36
@pattulloproject
Pattullo Bridge Replacement
2 months
Here’s a closer look at stay cable installation at the bridge tower. In this photo from August 4th, 66 of 80 total stay cables have been installed!
2
2
21
@pattulloproject
Pattullo Bridge Replacement
2 months
Bridge finishing works are underway on the main span! This work includes concrete finishing and the installation of safety fencing, lighting, utilities, and traffic barriers. The new bridge is 1,235 metres long and spans the 530 metre-wide Fraser River!
5
6
32
@pattulloproject
Pattullo Bridge Replacement
2 months
Check out this unique birds-eye view of stay cable installation from the top of the bridge tower! These strong cables are made of many metal strands in a protective tubing. They connect to the bridge tower and bridge deck to support the bridge structure.
3
6
36
@pattulloproject
Pattullo Bridge Replacement
2 months
In this photo from early July, crews are installing concrete deck panels on the ā€œend spanā€ – the final girders installed to connect the bridge deck from @CityofSurrey to the bridge tower. Once bridge deck construction is complete, paving will be done on top!
3
0
16
@pattulloproject
Pattullo Bridge Replacement
2 months
#PattulloBridgeReplacement finishing works continue on the main span bridge deck! Crews are busy working on concrete finishing and the installation of safety fencing, lighting, utilities, and traffic barriers.
4
8
41
@pattulloproject
Pattullo Bridge Replacement
2 months
Check out our latest flyover video! Stay cable installation is progressing, and finishing work can be seen underway for the main bridge span and the south approach in @CityofSurrey. In @New_Westminster, deck panel installation and concrete pours continue!
1
0
9
@pattulloproject
Pattullo Bridge Replacement
2 months
This photo was taken on July 7th in @New_Westminster! In this photo, you can see concrete deck panels installed over Columbia St and Front St. Deck panel installation continues on this side of the #PattulloBridgeReplacement.
2
2
19