2 days
Charging clearance has been conveyed to Northern Region Load dispatch centre for charging the 220 KV Barn Kishinpur Line, after completing the work of stringing the Tr.Line on new Towers.Awaiting the charging of Line from Kishenpur Grid now. @Divcomjammu @dmjammuofficial @diprjk.
1
0
16
@JKPTCL2019
JKPTCL Jammu
21 hours
Tweet media one
Tweet media two
0
0
1
@grok
Grok
7 days
Join millions who have switched to Grok.
254
503
4K
@JKPTCL2019
JKPTCL Jammu
21 hours
220KV KPTL has suffered Tower damage due to collapse of Towers at Location no 81 & at now at Loc no 62 in the intervening night of 1/09. The power to Bhaderwah ,Ramban ,Doda, Sangaldhan has been back fed through Mir Bazar Grid to meet exigency.There may be rotational curtailment.
1
4
11
@JKPTCL2019
JKPTCL Jammu
2 days
Streneous efforts being made by Team JKPTCL to complete the emergent works of erection of ERS at damaged tower Location no 46 of Bhattal Manwal transmission line feeding Vital Battal Manwal GSS alongside the expertise of PGCIL. Inconvenience Regretted.@RaheelaWani @Divcomjammu
Tweet media one
Tweet media two
Tweet media three
1
4
16
@JKPTCL2019
JKPTCL Jammu
2 days
220KVBKTL feeding all important Barn Grid was restored after untiring efforts of Team JKPTCL along with valuable help from PGCIL for allied works in persuit of successful completion of the works envisaged post the damage caused by Flood to this main trunk Line.@diprjk @Raj576113
Tweet media one
Tweet media two
6
7
43
@JKPTCL2019
JKPTCL Jammu
2 days
Barn Kishenpur Tr.Line Circuit -II stood ok and charged from Kishenpur at 1.58 am after following requisite protocols in coordination with Kishenpur.The Power supply which was affected on account of this will be restored to normal.@Divcomjammu @dmjammuofficial @JPDCLofficial FYI.
@JKPTCL2019
JKPTCL Jammu
2 days
Charging clearance has been conveyed to Northern Region Load dispatch centre for charging the 220 KV Barn Kishinpur Line, after completing the work of stringing the Tr.Line on new Towers.Awaiting the charging of Line from Kishenpur Grid now. @Divcomjammu @dmjammuofficial @diprjk.
7
2
18
@JKPTCL2019
JKPTCL Jammu
3 days
Today @RaheelaWani MD JKPTCL, @SanjaySharma_JK OSD PDD , RaviKant Kalsotra Ji Superintending Engineer continue to monitor the progress of works at Ground zero .Hope for early completion.
Tweet media one
Tweet media two
Tweet media three
9
5
25
@JKPTCL2019
JKPTCL Jammu
3 days
20MW load of Jourian and 15MW load of Rajouri was today met from alternative source during the complete shutdown of the Original source of 220KV BKTL . @Divcomjammu @dmjammuofficial @JPDCLofficial.
14
6
42
@JKPTCL2019
JKPTCL Jammu
3 days
RT @JPDCLofficial: Power Warriors making herculean efforts to restore 220KV Barn-Kishanpur Trans Line braving hostile weather. @CM_JnK @dip….
0
11
0
@JKPTCL2019
JKPTCL Jammu
3 days
Despite rains, despite risks involved , no looking back, JKPTCL Team is doing all possible to complete the envisaged works of 220 KV Barn Kishenpur Line. @Divcomjammu @diprjk @OfficeOfLGJandK
Tweet media one
Tweet media two
0
5
13
@JKPTCL2019
JKPTCL Jammu
3 days
RT @JPDCLofficial: MD,JPDCL & CE(D) today visited the site at Dhammi,where untiring efforts are being made to restore emergency works on 22….
0
9
0
@JKPTCL2019
JKPTCL Jammu
3 days
Untiring efforts are being made to complete the Restoration of the 220KV Barn Kishenpur Transmission line amid extremely adverse weather conditions , Senior officers MD JKPTCL MD JPDCL , CEs along with staff are camping at Site of Work to keep up the pace of work. @Divcomjammu
Tweet media one
Tweet media two
Tweet media three
Tweet media four
15
11
29
@JKPTCL2019
JKPTCL Jammu
4 days
Excellent work by Team JKPTCL Udhampur led by very energetic and dynamic Rajesh Sharma Ji Xen sb , Kewal Pathania AEE, Sumit Parihar , Pankaj, Zubair Neeraj Rohit Gul bhat.Kawaljeet JEs , who have done hardwork to restore power to ED Kishtwar @diprjk @Divcomjammu FYI.
6
3
28
@JKPTCL2019
JKPTCL Jammu
5 days
In a coordinated effort of JKPTCL & JPDCL, Power supply is being maintained on rotational basis to the areas which were likely to remain affected during this urgent shutdown of Barn Kishenpur line.@RaheelaWani @Divcomjammu @dmjammuofficial @JPDCLofficial @OfficeOfLGJandK @CM_JnK.
20
2
9
@JKPTCL2019
JKPTCL Jammu
6 days
To downstream network of Barn Grid shall be tried to be managed to some extent. Inconvenience Regretted @RaheelaWani @Divcomjammu @dmjammuofficial @JPDCLofficial FYI.
1
1
4
@JKPTCL2019
JKPTCL Jammu
6 days
In order to carry out immediate restoration of partial damage to the Barn Kishenpur Tr Line feeding 480 MVA , 220KV/132/33KV Barn Grid, shutdown has been approved from 06am 29/08 to 6pm 30/08.During this period, in order to reduce inconvenience, power supply on rotation basis 1/2.
17
5
44
@JKPTCL2019
JKPTCL Jammu
6 days
Power has been restored to both Canal and Pounichak Grids after restoration work has been completed.@RaheelaWani @JPDCLofficial FYI.
1
0
1
@JKPTCL2019
JKPTCL Jammu
6 days
132KV Barn-Canal line B1 &B 2 feeding Canal and Pounichak Grid tripped at 11.55 am from Barn Grid due to dropping of 220KV reserve bus conductor , and restoration work has been started. @RaheelaWani @JPDCLofficial FYI.
1
0
2
@JKPTCL2019
JKPTCL Jammu
7 days
132kv Miransahib chatha line charged at 5:50pm and stood ok. Chatha Grid charged. All 220KV &132 KV lines except 132kv line feeding Battal Manwal GSS are up and working.All Grids are charged. @RaheelaWani @Divcomjammu @JPDCLofficial FYi.
8
0
11