ArushiSF Profile Banner
Arushi Sharma Frank Profile
Arushi Sharma Frank

@ArushiSF

Followers
984
Following
1K
Media
233
Statuses
2K

Personal acct.Pvt Equity. CSIS. EmeraldAI. Big Batteries. Data Center Power & Grid Expert. Ex - TSLA, Constellation,EPSA,AGA,Tax Fdn. Lives on 🌍. STEM Lawyer.

Earth
Joined January 2024
Don't wanna be here? Send us removal request.
@ArushiSF
Arushi Sharma Frank
19 hours
@EmeraldAi_ @EPRINews #DCFlex.Packed day at Summer Seminar. Glad to be here w/ @vsiv. Super stoked to see APS SRP demos' flagship results shared with the US and multinational #datacenter investment ecosystem.
Tweet media one
1
0
5
@ArushiSF
Arushi Sharma Frank
19 hours
#DCFLex @EPRINews @EmeraldAi_ @nvidianewsroom Nvidia, all the hyperscalers, multiple cap table participants, and everybody talking about flex results from multiple demos. Very cool.
Tweet media one
0
0
1
@ArushiSF
Arushi Sharma Frank
4 days
RT @ArushiSF: A good report or two are out there on what we need long-term. This article is about what we could really use tomorrow/yesterd….
0
1
0
@ArushiSF
Arushi Sharma Frank
4 days
Tweet media one
0
0
0
@ArushiSF
Arushi Sharma Frank
4 days
A good report or two are out there on what we need long-term. This article is about what we could really use tomorrow/yesterday.
Tweet media one
1
1
1
@ArushiSF
Arushi Sharma Frank
4 days
AI workloads, pumped-up electrification targets. ERCOT, PJM, CAISO—they’re all buckling under queue congestion, load clustering, & 20th-century planning apparatus. That’s quite the problem statement. The answer, we posit, is Gas + X.
Tweet media one
5
2
7
@ArushiSF
Arushi Sharma Frank
4 days
"While not meaningless, historical utility dd forecasts consistently .overestimate both peak and average demand. Rigorous models of data center energy use are needed to adequately calibrate both future investment and public .concern."
@ShanuMathew93
Shanu Mathew
4 days
VERY important piece @tylerhnorris!. Data centers may not run at 90%+ capacity 24/7 as widely believed. Key confusion: load factor ≠ utilization rate. Maintenance, hardware failures, workload variation, & thermal limits mean lower usage, but utilities plan around peal demand.
Tweet media one
Tweet media two
Tweet media three
Tweet media four
1
1
10
@ArushiSF
Arushi Sharma Frank
4 days
Utilities consistently emphasize data centers- specifically AI as drivers of projected .increases in electricity dd. In parallel, specialized microelectronics analysts made more reserved estimates of short- and medium-term load growth due to greater emphasis on .manufacturing.
0
0
0
@ArushiSF
Arushi Sharma Frank
4 days
"@Microsoft challenged Georgia Power’s modeling methods, highlighting concerns .that the model is undervaluing renewable energy while overestimating data center load for projects that have not yet selected Georgia Power as their provider (Allsup 2024)."
0
0
0
@ArushiSF
Arushi Sharma Frank
4 days
0
0
0
@ArushiSF
Arushi Sharma Frank
4 days
Tech and reg - are working against each other w/ a grid connect planning framework which is risk-averse, static. It's largely a behavioral incentives problem across two sectors which don't quite chat with each other at the level they should.
Tweet card summary image
csis.org
Power utilities still plan for worst-case scenarios in both grid forecasting and interconnection studies. But AI data centers do not have to be built—or operated—in ways that trigger those worst-case...
2
2
2
@ArushiSF
Arushi Sharma Frank
4 days
Contrary to the assumption of constant high utilization, this strategy reflects real-world variability, challenging the narrative of data centers as always-on loads, supported by utility reports citing actual load factors of 80-85% versus planned 90%. @tylerhnorris @ShanuMathew93.
1
0
3
@ArushiSF
Arushi Sharma Frank
4 days
This approach drives regional network upgrades rather than site-specific ones, aligning with findings from the 2024 United States Data Center Energy Usage Report (LBNL-2001637), which notes data centers often operate below 90% capacity due to maintenance and thermal limits.
2
1
2
@ArushiSF
Arushi Sharma Frank
4 days
Utilities plan for loads to have firm demand - all the time. They assess load contribution to system peak and apply the tail risk analysis for all hours as firm dd. That goes into area network upgrade analysis. The upgrades are regionally planned this way, not just for one site.
@ShanuMathew93
Shanu Mathew
4 days
VERY important piece @tylerhnorris!. Data centers may not run at 90%+ capacity 24/7 as widely believed. Key confusion: load factor ≠ utilization rate. Maintenance, hardware failures, workload variation, & thermal limits mean lower usage, but utilities plan around peal demand.
Tweet media one
Tweet media two
Tweet media three
Tweet media four
2
2
17
@ArushiSF
Arushi Sharma Frank
4 days
RT @duncan__c: On new years day of 2023 @DER_Task_Force released a pod titled "The Clean Energy Abundance Platform". In it we broke down h….
0
5
0
@ArushiSF
Arushi Sharma Frank
4 days
I hear this from friends in other countries too. Most recently, in Buenos Aires.
@duncan__c
Duncan S. Campbell
5 days
Spoke to a Chinese friend today who was recently home in a Chinese major city for a few weeks. He said al of his late 20s friends are bummed out and don’t think their futures will be good. 9-9-6 is real but the work is performative to keep your boss happy. All bullshit. Tons.
0
0
0
@ArushiSF
Arushi Sharma Frank
5 days
RT @JLopas: @ArushiSF @basepowerco Can confirm the gong was hit for this one 🔨.
0
1
0
@ArushiSF
Arushi Sharma Frank
5 days
There is also a GONG. I have whacked it. @basepowerco .Kudos to those lucky enough to attend their IEEE afterparty/Salon at HQ. The lab setup and the house demo are also 🔥.
@JLopas
Justin Lopas
6 days
We track tons and tons of metrics. This is the number you see when you first walk in the front door of the office @basepowerco . This one - and its rate of change - matters the most.
Tweet media one
2
0
10
@ArushiSF
Arushi Sharma Frank
5 days
RT @ZachBDell: As the old saying goes, the first 100 MWh is the hardest…
Tweet media one
0
25
0
@ArushiSF
Arushi Sharma Frank
6 days
Capacity shortfalls in West London, data centers competing with new industrial parks. Can't validate accuracy, but can say the post is worth a quick look.
Tweet card summary image
linkedin.com
It’s already hard enough to get a grid connection in London. Now it’s about to become nearly impossible. Are you feeling the pinch? London is now second only to California as the world’s largest data...
0
0
0