Tracking The Status Of Implementation Of Metro Project In Bangalore Independently
Bangalore
Joined November 2025
A mockup of Platform Screen Door is installed at MG Road underground station of Pink Line. Checkout more details in today's DH article by @ever_pessimist : https://t.co/4PJlNnIJCf
#BMRCL #NammaMetro
0
4
46
6th train for #YellowLine One coach is arriving in Bengaluru tonight, two more tomorrow night, and the remaining three next week. This train will enter passenger service around 3rd week of Dec. Expect peak-hour frequency of 12 mins. @WF_Watcher @blrmetrotracker
3 coaches of Trainset 6 for #BengaluruMetro’s #YellowLine have been sent by TRSL; 3 more leave tomorrow. The train will arrive by Nov-end. Once inducted in Dec, it'll improve freq. to 12–13 mins. 2 more trains are in the works; expect 10-min freq. @WF_Watcher @blrmetrotracker
6
15
133
Sheet Changelog : 28-11-2025 Afcons: • Iblur Red Station P2R GL To CL Tied • Iblur Red Station P2M GL To CL Formwork Assembled • Iblur Red Station P3L Pile Excavated NCC P1: • AP315R Rebar Up • HBR Station P6 CPC Launched • Horamavu Station P3 2x CC Arms Completed NCC
4
1
34
Request not to tag me in such posts. Generic posts like these without specific information isn't just unhelpful but also feels spammy. For example, the post does not specify the nature of the work being bid upon, the package, the stretch. Without specifics, a layman would think
🚇 Bangalore Metro Phase 3A: Connecting Sarjapur to Hebbal 🚨 With 36.6 km of transformative corridor- 22.14 km elevated, 14.45 km underground, and 28 modern stations- Phase 3A promises to redefine connectivity in Bengaluru’s fastest-growing corridors. 💰 Estimated at ₹28,400
0
3
67
Update on the Hebbal flyover Loop Remodeling - 28-Nov-2025 Span erection completed on all 3 ✅ Slab Cast on 1 of 3 and 2 more to go . Kudos to @BDAOfficialGok and PJB Engineers
Update on the Hebbal flyover Loop Remodelling. 2 Spans removed. ✅ Portal beam removed. ✅ Old Pier removed ✅ Piling ✅ Pier Casting ✅ Pier Cap casting✅ Span Erection : 1 ✅and 2 more ⏳
4
13
129
Sheet Changelog : 27-11-2025 Afcons: • Silkboard Station P4-P5 5x CCL IG Launched • Silkboard Station P8-P9 6x PFL IG Launched • Iblur Red Station P1M GL To CL Cast • Iblur Red Station P1R GL To CL Being Tied • Iblur Red Station P2M GL To CL Tied • Iblur Red Station P2R GL
5
7
57
Delhi metro to develop customised data management system for BMRCL @blrmetrotracker
DMRC @OfficialDMRC has floated tender for Integrated Data Management System (IDMS) for BMRCL @OfficialBMRCL Request additional information on this. Why is DMRC floating tender for BMRCL, what is this project about, would it be centralized system for DMRC & BMRCL or dedicated
3
4
42
Just like how the garbage issue is being dealt with these days, this poster menace too should be meted out similar treatment by fining them heavily & making them clean these. @GBAChiefComm @GBA_office
Posters pasted on Jayadeva metro station building #YellowLine. Dont they feel anything that they are disfiguring the building? Spoiling the nice facade!! 😡 No civic sense? @OfficialBMRCL @srivasrbmrccoi1
@ChristinMP_ @ever_pessimist
0
5
61
After over 3 years, @KridePrm gets a technocrat as its MD. Rly board approves the deputation of Lakshman Singh, a 1996-batch IRSE official, to K-RIDE for 3 years. Singh is currently CGM (Civil), Airport Line, P1 (KR Puram-Hebbal), at @OfficialBMRCL. @WF_Watcher @blrmetrotracker
5
11
63
Posters pasted on Jayadeva metro station building #YellowLine. Dont they feel anything that they are disfiguring the building? Spoiling the nice facade!! 😡 No civic sense? @OfficialBMRCL @srivasrbmrccoi1
@ChristinMP_ @ever_pessimist
22
53
249
🩷🚆 BEML awards tender for transportation of Pink Line (R6) and future Blue Line trains (2A-2B) from BEML manufacturing facility to Kothanur Depot (R6), Baiyappanahalli Depot (2A) & Airport Depot (2B). With the promise of delivery of 1st Pink Line prototype train next month
11
47
431
Sheet Changelog : 26-11-2025 Afcons: • ORP167L Cast NCC P1: • Veerannapalya Station P2 L PD To CL Cast • AP270L Rebar Up • AP193L : L1 Formwork Assembled • AP187 Support For Midbeam • Horamavu Station P4 2x CC Arms Completed • Veerannapalya Station P2 R PD To CL Being
0
1
29
Centre approved Thane Ring Metro and Bangalore Metro Phase 3 together in Aug '24. 15 months later, MahaMetro already finished the long bidding process and will start work in Dec/Jan. Meanwhile INC KN continue to waste time over road tunnels they dont have money for.
Centre approved Rs. 12,200Cr Thane Internal Ring Metro. With MH State Elections delayed, is it possible to award Civil Contracts before model code of conduct? One would assume CM Eknath Shinde would be motivated to push it through.
9
45
279
Steep Ramp built on footpath opposite Metro Pillar 20 on Greenline. 8th Block Jayanagar. People forced walk on a busy road risking accidents/injury. Request @GBAChiefComm @blrcitytraffic to get this removed & provide level footpath. #PedestriansHaveRightToWalkSafely @TOIIndiaNews
8
14
92
finally some sign of life, of the Kadugodi extension.. some inspection work by MVR and BMRCL, probably to align with ongoing BWSSB cauvery line digging.
@OfficialBMRCL Any update on this Purple Line extension, 588m extension? This will help public to board from Kadugodi side. https://t.co/vSAerVTTCX Some study happned in 2023, and now some digging is happening. cc @WF_Watcher @WFRising @ChristinMP_ @SaveKadugodi @ForceGW
0
3
29
DMRC @OfficialDMRC has floated tender for Integrated Data Management System (IDMS) for BMRCL @OfficialBMRCL Request additional information on this. Why is DMRC floating tender for BMRCL, what is this project about, would it be centralized system for DMRC & BMRCL or dedicated
4
5
34
Sheet Changelog : 25-11-2025 NCC P1: • Horamavu Station P4 1x CC Arms Completed • Kasturinagara Station P8 CL To TL Tied • AP1R Rebar Up • AP254L Pile Excavated • AP266 Pier Cap Collar Ring Fixed NCC P2: • UP-AP366L Tied • UP-AP356 Tied • Kodigehalli Station P5 PF Beam
1
2
35
Have added an initial set of Frequently Asked Questions (FAQ) section on the website. Let me know if any additional questions need to be added. Check it out at: https://t.co/vExOf3Jl7F
#BMRCL #NammaMetro
12
7
64